TechnoArt Engineering completed the renovation of the First Floor of AWT Tower Lahore, creating a modern and functional space. The work included flooring, ceilings, and advanced electrical systems, along with networking, CCTV, and HVAC upgrades. Stylish glass partitions, wooden grid ceilings, and custom workstations with cabinets enhanced the design. Plumbing systems and branding elements were also integrated to align with the project’s goals. This project reflects our ability to deliver efficient and well-designed solutions tailored to client requirements.

 

 

AWT Tower Lahore 1

The Challenge of Projects

Renovating the First Floor of AWT Tower Lahore had its challenges. Coordinating tasks like flooring, ceilings, plumbing, and branding required detailed planning within a tight schedule. Installing systems like electrical, networking, CCTV, and HVAC needed precision to ensure everything worked smoothly. Designing glass partitions, wooden ceilings, and custom workstations added to the complexity. Completing all this while minimizing disruptions in an active space was a key test of efficiency and expertise, showcasing our ability to deliver high-quality results.

 

 

AWT Tower Lahore 3
  • Managing multiple tasks like flooring, ceilings, and plumbing within a tight timeline.
  • Installing electrical, networking, CCTV, and HVAC systems with precision.
  • Ensuring smooth coordination of design elements like glass partitions and wooden ceilings.
  • Creating functional and customized workstations and cabinets.
  • Integrating branding elements seamlessly into the space.
  • Minimizing disruptions in an active workspace.
  • Maintaining high-quality standards throughout the project.

Scope of Work

  • Flooring
  • Ceiling
  • Electrical
  • Networking & CCTV
  • HVAC
  • Glass Partition
  • Wooden Grid Ceiling
  • Workstations & Cabinets
  • Branding
  • Plumbing

Project Information

  • Client:
    Pak Arab Refinery Ltd.
  • Category:
    RENOVATION
  • Start Date:
    June-2022
  • End Date:
    September - 2023
  • Tag:
    Completed, Signature
  • Amount
    Budget: Rs. 65,642,073.00